MINUTES

January 31, 2005  Highway 2 Safety Coalition Meeting

Community Center Room

319 Main Street

Sultan, Washington 98294

 

Meeting called to order at  7:06 PM

 

Attendees:

 

  • Fred Walser, H2SC Chairman
  • Donnetta Walser, Mayor of City of Monroe
  • C. H. Rower, former Mayor, City of Sultan and H2SC Charter member
  • John Seehuus, Councilman, City of Sultan and H2SC Charter Member
  • Jim Flower, Councilman, City of Sultan
  • Kamuron Gurol,  Corridor Planning Mgr., Urban Planning Office, WSDOT,
  • Loreena Eng, P.E., Regional Administrator, Northwest Region, WSDOT
  • Rick Mitchell, WSDOT (no title available for these minutes)
  • Tina Rogers, Snohomish County Public Works Department (no title available for these minutes)
  • Lonn Turner, Councilman, City of Gold Bar
  • John Light, Public Works Director, City of Gold Bar (filling in for Mayor Hawkins)
  • Connie Dunn, Public Works Director, City of Sultan
  • Jerry Schutz, Stevens Pass Greenway
  • Jerry Slader [spelling uncertain], Stevens Pass Greenway
  • George Schmidt, Stevens Pass Resort
  • Frank Linth, Century 21 Real Estate, Monroe
  • Kathy Wilson, Century 21 Real Estate
  • Loretta Storm, Temporary H2SC Secretary

 

 

Chairman Fred Walser announced the  $500,000 Federal Omnibus funding which was received, to be applied toward the Rural Route Corridor Study for Hwy. 2.  Workgroup members (representatives from Hwy. 2 corridor cities) met and reviewed priorities on how to utilize this funding, as well as identifying additional priorities to match this initial $500,000. 

 

Mayor Donnetta Walser briefly summarized the initial strategy that was developed.  Kamuron Gurol has been instrumental assisting with that.  Hiller West, Monroe’s Community Development Director, wrote the federal revenue request which resulted in the Omnibus funding.  The Rural Route Corridor applications are due to be issued February 1, 2005, with a deadline for application submittal of April, 2005.  The strategy they developed was that Mr. Gurol would assist with the data and research required (i.e., LOS, statistical assistance, etc.), and Hiller West coordinating with WSDOT for actual writing, assigning questions and assembling the information.  Not sure at this point precisely what is needed, but Tina Rogers and Kamuron Gurol were going to contact King County and encourage them to get on board.  Additionally, the Stevens Pass Greenway’s interest in participating in the overall effort adds more weight and scope to the H2SC’s efforts.

 

Mayor Walser explained a key component is to present the plan to Snohomish County Tomorrow (STC) no later than March to obtain their support in this effort.  She explained that at least part of that process is to first obtain  the City of Sultan’s formal agreement. Complicating things a bit is that  both Sultan’s and Monroe’s councils (and the STC) all meet on Wednesday, so presentation of the plans is challenging. One of Monroe’s councilmen, Jeffrey {sounds like, “Hahn”], attends STC, and he’ll be briefed to ensure that it is placed on SCT’s agenda.

 

Chairman Fred Walser read the following email he received from Hiller West:  “I received a return phone call from John Dewhurst (Snohomish County) to inform me that our request for corridor funding has already been placed on the agenda for the next Infrastructure Coordinating Committee --  ICC – meeting on February 11th.  It is not necessary to submit anything in advance, so if possible, it may be more effective to provide a draft of the project description and/or application so that committee members will have a better idea of what is being discussed.  John also stated that the application will also be placed on the March agenda for the Snohomish County Tomorrow Executive Committee.  He says this should be verified after the ICC meeting with Peter Hahn at the county.” 

 

Jerry Schutz (Stevens Pass Greenway) offered a summary of their involvement in the Rural Route Corridor effort.  Last year their group performed a multi-modal study, encompassing all modes of travel, including highway traffic, rail service, increased/enhanced bus service (both public and private), bike and pedestrians, especially related to making more accessibility to recreational opportunities for the Cascade/Highway 2 region.  They were ready to speak with legislative representatives to obtain support.  He’s been speaking with King Cushman (PRSC) for some time regarding the same Rural Route funding, and he’s been very supportive.  Then approximately 10 days ago he received a call from WSDOT and he discovered that Kamuron Gurol, who used to be on the Greenway’s board, is now heading the WSDOT route program.  They mutually decided that it wasn’t in anybody’s best interests for several entities to be competing for the same funds, basically for the same transportation corridor.  So the Greenway wishes to join this effort for now, and if it doesn’t work, then they’ll try to find some other option.  For now, the Greenway will be added as an active participant/member of the Coalition.

 

Fred Walser explained that during their recent meeting, which was attended by Kamuron, John Light, Connie Dunn, Mayor Walser, John Dewhurst and Chairman Walser, that issue was discussed and decided it was logical and beneficial to partner with the Greenway, just as it is logical to partner with King County; the more parties join the overall effort, the better their chances of success.  So the goal is to work in tandem with other groups’ efforts. In response to Mr. Schutz inquiry about their contact at King County, Tina Rogers said they’ve been working with [sounds like either, “John” or “Don” Ding], who also participated in a recent 203 project.  So several people will be working together from the technical fields, although they will probably not be attending the H2SC meetings. Jerry mentioned that his King County has been Doug Ingleson  [spelling uncertain], who has been very helpful and attended several of the Greenway’s workshops.

 

 Kamuron Gurol arrived.  He was driving in from Auburn and arrived late.  He then provided an update of the Rural Route Program, funding, etc.  (See the essentially word-for-word transcription which follows these minutes.)

 

Tina Rogers offered that the PRSC application is Due April 1st at 1:00 PM, with the decision made in June.  The potential exists that in May, applicants may need to make a short presentation to the ICC steering committee of their programs.  She sites on that committee.  Potentially there are as many as three projects under consideration.  She does not know how much competition exists at the ICC level.

 

Jerry Schutz (in response to a question from Gurol), indicated that the Greenway will cooperate with H2SC on those portions impacting them, and modify their proposal accordingly.  Looking at train service in the corridor probably fits outside of the RDP process, as well as a few other things, such as private bus service, so they will probably move forward individually on those types of things.  But regarding safety issues, they will offer statistics taken over the last few years relative to previous safety problems in the hope of ensuring that such statistics do not occur in the future.  Mr. Schutz reinforced his belief that the Coalition’s efforts compliment, rather than conflict, with the Greenway’s interests, overall.

 

Gurol reinforced and encouraged continued of the work group concept, but indicated that he did not have a good understanding of the individual cities’ efforts taken within their city limits related to U.S. 2.  Even a subarea plan or access management plan ought to be coordinated within the overall Route Development Plan, if possible.  He indicated that this rural corridor includes many contradictory agendas, such as strong Economic development interests vs. conservative environmental concerns, etc., so there will be many different opinions/plans put forth.

 

Gurol indicated realism related to the amount of funding the Coalition may receive, urging a pragmatic view of what funds may be available and/or received.  There’s a lot of competition for funding across the region, despite the U.S. 2 corridor’s “worthiness,” and it’s best to be both realistic and honest with stakeholders throughout the process.

 

Mayor Walser shared what occurred during her and Fred’s visit with Washington’s Congressional delegation in Washington D.C.:  She said the primary problem in obtaining funding was they did not first have a completed study and project.  It’s a Catch-22:  Project and study leads, and funding follows.  Her input from Valley legislators is that anything that helps any city, or alleviates any problems on U. S. 2 will benefit all cities/areas.  But priority identification is the place to begin.

 

Tina Rogers enumerated some of the key decision points, which included a definition of the dollar amount requested from PSRC; how much to apply for, as specified on application; be realistic. (Mayor Walser suggested that the Coalition should request as much as possible, $3 million minimum to get started; Chairman Walser clarified they had originally asked the Delegation for $8 million.)  Rogers indicated  that a study costs between $100,000 to $200,000, and available PSRC funds must be spread across many jurisdictions.  The  funds are available in Jan., 2006, so PSRC funds should be considered as just another phase of the planning effort. What does the Coalition need from the county now and who in the Coalition will make the decision or give approval? (Mayor Walser believes plan approval will come from corridor’s mayors.) The ICC will develop a process by which to evaluate the best applications being presented to PSRC.  The ICC is comprised of public works directors and staff, who make recommendations to the SCT Steering Committee.  It’s her understanding that each county will be limited to two  applications, or potentially three, if it crosses a county line. The February SCT meeting will reveal the number of applications that will be submitted, and a recommendation is hoping to be made in March. The dollar amount requested could affect decision-making at both the ICC and SCT level, so she urged caution at being “too greedy.”  The PSRC wishes to fund more than one planning effort, as well as having money set aside/used for communities which have already submitted their plans, such as the 203 or 532 corridors, and ideally, also funding some capital construction.

 

Gurol and Fred Walser suggested next best step is to form small workgroup to address specifics of application.

 

Tina Rogers indicated that for the purpose of presenting to the PSRC, it could be as simple as “Monroe plans to take a lead on an application for the U.S. 2 Corridor from Snohomish to Skykomish.  We’re thinking in the neighborhood of $100,000 to $200,000 to match the $500,000 federal funds on hand,” although she mentioned that the March application process would require a bit more detail and documented support.  Another key step is obtaining letters of support (interested organizations, individual cities, et al.), as well as a joint city resolution.  Suggested that all cities address a resolution in their March council meeting(s).

 

Chairman Walser indicated timeline is tight:  ICC meeting is 2/11.

 

Rogers also mentioned matching funds; actual staff costs could be used for matching PSRC funds; i.e., attending meetings, etc. Mayor Walser said cities’ consensus was to use city staff time with this purpose in mind.

 

General Discussion ensued related to PSRC funding being federal dollars; letters of support, other general details in moving ahead with application.

 

Gurol urged clarity and specificity insofar as approval for the RDP as related to individual cities’ municipal process; i.e., product needs to be “consensus-based” which incorporates much public process, and, therefore, buy-off from each city’s officials.  May wish to develop a “Policy Group” comprised of elected officials, along with several layers of decision-making/authority.  Ultimately, “high level” approval is required from jurisdictions.

 

Meeting adjourned 8:38 PM

[Minutes Authored and submitted by H2SC Temporary Secretary L. Storm]

 

 

TRANSCRIPTION: KAMURON GUROL’S SUMMARY/EXPLANATION OF THE ROUTE DEVELOPMENT PLAN PROCESS

 

I work in the Urban Planning Office in Seattle.  And our job is to do route development plans for King and Snohomish counties.  And I’d like to talk to you a little bit about the Route Development Plan (RDP) process, which looks like that’s the use that the first federal funding, at least, will be used for.  And depending on how many other sources of funding can be identified, we would essentially add to the scope of work for that process.  So what I’m going to talk to you tonight is – I’ve got a generic hand-out on what the Route Development Process is.  I sent out a weblink this afternoon in response to your meeting invitation.  Hopefully you got copied on that, which gives my contact information as well as other materials you might find interest in. I’m sorry I was late.  I came up from Auburn, talking to the city council about one of the other processes and just got through.

 

What I’m handing out is a generic description of what Route Development Plans, and a simplified timeline for the major steps involved in producing a plan.  And if, indeed, we got down this road of putting together a Route Development Plan, we would be working – WSDOT would kind of be the lead agency for this  -- we’d be working with partner agencies along the corridor route. So the cities and the counties, as well as the Puget Sound Regional Council (PSRC), in terms of the government entities [unintelligible] along the route.  Then there’s a whole variety of interest groups and stakeholders that would be part of the process, as well.  Now you’re looking at your scope of work and trying to see where things fit. 

 

Our office right now has about four of these projects in active process.  In King County at the moment, we’ve got two more coming online.  This is one of them, the other one is down in King County.  Typically these processes can take anywhere from six months up to a year. They probably average somewhere about 12 months, but the time depends on the complexities of the issues, the length of the route – and this is a pretty long segment that we’re dealing with – so far the focus is between Snohomish and Skykomish and the two ends there have not been completely cemented in terms of our start and finish point.  But that’s the portion of the corridor that seems to have a good deal of the safety and congestion problems because of the urban areas that are along there and the various speeds.  You have 55 and people driving faster, down to 35 in towns, with a lot of land use conflicts like driveways, individual homes on driveways, businesses [unintelligible; drops his voice].  And what you want to have – what the Route Development Planning process allows you to do is to look at all the different segments that you have in an individualized fashion collectively and try to identify the problems correctly – whether it’s a safety problem or an awkward alignment or a volume of traffic problem or some combination, and then identify the different solutions to that problem and then [unintelligible] against the criteria that you develop to test the effectiveness, cost-effectiveness, environment impact and so forth.  And then you identify a series of projects that would be proposed for funding from some source to actually address all those problems.  So it’s kind of setting up a gameplan for getting those problem areas addressed. 

 

It takes awhile to do this.  As I said, it might be somewhere within a year, but it depends on how the process goes.  We’ve got to get going on it soon.  I think we have to work with the partner agencies, exactly what the scope of work looks like. Typically, a consultant is hired to help review the mountains of information collected, evaluate the various proposed projects, and then issue the product:   The Route Development Plan.  The State officially adopts the Plan, which means the state will attempt to follow it, in part by using it in the state budgeting/funding process. We’ve also employed valuable mechanisms to help local agencies also adopt it such that there’s a consistency in implementation of the Plan over the course of time.  So ideally, all these different cities will somehow participate in the process, agree with the proposed solutions to the problems, and then adopt the Plan in their own jurisdiction and the part that is their responsibility to implement.

 

The cost of funding is enormous.  And there’s not that much money out there available.  So you have to do the best job you possibly can.  The Route Development Planning process allows you that opportunity.  I want to thank whoever put together, had the good sense of getting the first Feds funds earmarked.  I think it’s a wonderful thing.  It’s a real bonus to me.  It’s about the same level of money that the State has contributed for two other RDPs that we’re looking at in King County right now; one of them is SR 164 in Auburn, and one for SR 169.  Those two routes share some similarities to US 2, that is, they’re both in urban/rural areas and they’ve got all the problems that you might have in a relatively urbanized area, like in Monroe and you have some problems in some smaller towns as well.  And then speed differentials along the whole route.  But they’re a lot shorter.  SR 169 is somewhere around 30 miles and 164 is about 20 miles.  So right now, I think we’re on the 45- to 50-mile length, somewhere in that category, for this one.  So it’s a bigger highway area, slice.

 

So what we’ve done so far is to start collecting a bunch of data, a couple of maps, if anybody’s interested.  We’ve got some statistics for the number of trips, how many cars come along the roadway, where you find the high-accident locations, and we’ll certainly collect information that’s coming out of the State’s system plan for projects that have been identified by previous versions of me [unintelligible; someone coughs] put in to the state’s plan, and just kind of pull together all the background information. So then we can develop the first, second and third steps for you for getting this project underway. 

 

This is my third meeting on this project.  I attended a meeting of elected officials, the small group I met last week, staff and elected officials that were, I think two things:  trying to look at the different funding sources for this RDP process, and then also talking about what are the elements and components that are put in these things.  Because I think there’s some latitude.  That is, we have some flexibility to address issues that are specific to this corridor.  So we want to tailor the components and analyses  specific to U. S. 2.

 

Re funding issues, etc.:   So as I know right now, we’ve got the first $500,000 earmarked.  We’ve got an opportunity to apply for, and to actually secure some funding from the Puget Sound Regional Council under their Rural Corridors Program.  We’re going to talk about that.  I believe Hiller, who’s in effect the regional planning director for Monroe, will take the lead in putting that application together. The form’s supposed to be available tomorrow, so we can start doing that.  I think there’ll be a lot of contributors to that, and our office will certainly try to put that application forward in the best possible light.  But we have to be careful, too, working for the State, that [unintelligible] in a similar position that this isn’t the only road out there.  As I said, I just came from Auburn, so we’ve got to be careful to be as equity-minded as possible between different routes around in our region here.

 

So that’s one source of funding.  I don’t know how much, if any, has occurred there.  There’s a $2 million pot over two years that can be allocated to both planning studies as well as capital projects.  And they’re trying to, within the four counties of PRSC, see that it’s distributed in a roughly equitable basis.  It won’t all come to this project.  I think we’ll be fortunate to get some portion [unintelligible; drops his voice].  Staff can keep an eye on that and kind of report back as that process moves forward.  We’re told by the PSRC staff that applications are going to be due somewhere in April and I think they’re going to decide in [unintelligible]. 

 

[Gurol’s presentation was interrupted by input from Tina Rogers and Jerry Schutz, then he continues.]

 

So just so you’re familiar with this, the Route Development Plan is kind of what I’ve already described there.   This flow chart I “stole” from another RDP in the region, so the specifics included in the base here, I would not pay attention to, but it basically shows the overall process.  It is a public process that we undertake.  We do outreach, we do open houses, we’ve got to coordinate with city council meetings, other types of events or locations where it would maximize our chance to interact with people who use the route, because they provide us with the best information about what we need in that Route Development Plan. So there’s, I would think for a route like this we would have at least two rounds of open houses, possibly even three, depending on the length of the study.  We’d be out soliciting ideas and getting feedback on the different alternatives that we’ll create.  That’s what we’re doing down on the other two RDPs that I mentioned to you.  We’re going to open houses in early March.  As I said, there is typically a consultant hired.  We do rely on some city staff, particularly participation in meetings, providing information.  WSDOT is kind of the lead on the project, coordinator; the county, PSRC, all the kind of relative jurisdictions would participate.  We also would have the opportunity to identify stakeholder groups and we can tailor the process for the needs of the corridor.  What I would want to do is create a process to give us the best information and the most efficient possible.  I’m not interested in creating loads of committees that meet all the time and [unintelligible], nor on the other end of the spectrum, which is WSDOT does this and tells you what happened later and you say, “Well, [unintelligible] have to do with me?”  So it’s somewhere in the middle, where we find the right people to get involved and we get the best information efficiently.

 

 So if I had to guess, from start to finish, it could be anywhere from 12 to 18 months until you get one of these things done.  It’s good to also keep note of the state legislative cycle as you go through one of these things. So even  if we’re not done by the time the 2006 legislature meets, you’ll want to identify some things that we already know, and if there’s an opportunity there to [unintelligible]  funds and things, and you feel confident enough that these are good projects and [unintelligible].  My guess is that some of the cities or the county may have already identified some projects and proposals for funding in this legislative cycle.  And if they get funded and vote, why then, that’d be great and we’ll incorporate that into our plan.  So you’ll need to keep you eye on that ball.  The legislative cycle is one cycle, the federal funding cycle is another cycle.  You know, all these things just sort of come up from time-to-time and [you] try to tailor the process so that you’ll have some good information to feed into whatever cycle you’re in. (end of transcription)