SULTAN CITY COUNCIL

AGENDA ITEM COVER SHEET

ITEM NO: Action A 3

DATE: February 20, 2002

SUBJECT: Sewer System Inflow & Infiltration Removal Program

CONTACT PERSON: Public Works Director Dunn

Acting City Engineer Bourne

SUMMARY: At the Council Workshop on February 6th the issues of I&I (excess water) in the City’s sewer system and the impacts on the Treatment Plant were briefly discussed. The problem and potential solutions are explained in further detail in the attached February 14, 2002 Memoranda. The first step of the two Phase Program is to proceed with the design of repairs for the known problem locations as mentioned is the Memo. A set of drawings and specifications will be prepared that will describe the method of repair for each problem location. In addition this work will prepare two grant applications for the design and construction of Phase 2. The attached Task Order 2002-8 is to be accomplished under the existing Contract for City Engineer. It is anticipated that a contractor selected from the City’s Public works Roster will accomplish the actual construction as soon as design is complete.

ATTACHMENTS: February 14, 2002 Memo Re: Inflow and Infiltration Impacts on Wastewater Treatment Plant

Task Order 2002-05

FISCAL IMPACT: The CR Fund will be used to fund the anticipated $27,000 for the engineering and grant work in Phase 1.

RECOMMENDED

ACTION: Authorize the Mayor to sign Task Order 2002-8 in order that Berryman and Henigar may proceed with design plans for the removal of I&I from the City’s sewer system.

 

 

 

February 14, 2002

 C. H. Rowe, Mayor
City of Sultan
P.O. Box 1199
Sultan, WA 98294

RE: Task Order 2002-05 to Professional Services Agreement dated March 1, 1999 for City Engineer Services

Phases I & II for Inflow and Infiltration (I&I) Reduction Program

Dear Mayor. Rowe:

We have completed the attached memo dated February 14, 2002 regarding the I&I impacts on the sewage treatment plant in accordance with the City’s Task Order 2002-03. A schedule and budget for Phases I and II of the I&I reduction program developed in the memo are attached.

In accordance with the Professional Services Agreement between the City of Sultan (City) and Berryman and Henigar (B&H) dated March 1, 1999, we have been asked to continue our services as acting City Engineer to initiate the I&I reduction program.

This work of preparing the I&I Reduction Program will include the following services:

PHASE I

PHASE II

  

We anticipate completing engineering in Phase I and the loan applications in Phase II for the Inflow and Infiltration (I&I) Reduction Program and have it ready for a staff presentation to the City Council in May 2002. The estimated budget for this work is $27,000.

Sincerely,

 

 

 

 

Gary Bourne, Regional Manager C. H. Rowe, Mayor

Berryman & Henigar

 

 

Connie Dunn, Public Works Director

 

Memo

Date: February 14, 2002

To: Connie Dunn, Public Works Director

From: Gary Bourne, Acting City Engineer

Re: Inflow and Infiltration Impacts on the Wastewater Treatment Plant

 

SUMMARY

City Staff has been preparing to initiate the work necessary for the removal of excess inflow and infiltration (I&I) from the City’s sewer system. From 1991 to 1997 there were a number of studies and reports that documented sources of I & I in the City’s sewer system. Although City staff has eliminated a number of these I & I sources over the last few years, numerous problem locations remain. In addition, there will be new sources of I & I that have not been identified.

Removal of excess I&I from the City sewer system has become more important in the last couple of years as excess water in the system will begin to reduce the treatment capacity of the City’s wastewater treatment plant. This was recently demonstrated during the heavy rains in November that caused the peak flows to tax the capacity of the Wastewater Treatment Plant (WWTP).

However, the ability of the WWTP to treat flows is not measured on peak flows, rather on average flows. The average flows during the summer months of 2001 were in the range of 250,000 gallons per day (0.25 mgd). During the month of November the average flows were in the range of 0.35 mgd. The capacity of the WWTP to treat average flows is in the range of 0.78 mgd. Present average flows indicate a current population of approximately 2,500 people connected to the sewer system.. The design population of the WWTP is about 4,800 people connected. All of this indicates that the size and capacity of treatment plant is not the problem.

Industry and treatment design standards would normally consider I&I to be a problem when the peak flows exceed average design flows by a factor of five or greater. Recent peak flows at the WWTP exceeded 2.2 mgd which results in an I&I peak flow factor of 8, indicating a significant I&I problem. An I&I problem that is reducing the use of the WWTP for treating new customers.

This memorandum will discuss the I&I issue and identify recommended actions. Although an I&I reduction project will require an extracted effort over an extended period of time, it is recommended that the most significant sources of inflow be eliminated as soon as possible.

The 1997 Comprehensive Wastewater Plan established an estimated budget for this I&I removal work of $240,000. The City’s current sewer rate structure includes those costs as part of the utilities capital budget.

Infiltration and Inflow

Infiltration and inflow (I&I) is storm and/or ground water that enters the sewer system through cracked pipes, leaky manholes, or improperly connected storm drains, down spouts and sump pumps. Most inflow comes from stormwater and most infiltration comes from ground water. I&I affects the size of Sultan’s sewer pipes and treatment plant, and ultimately the costs of operating those systems.

Infiltration quantities typically exhibit seasonal variation in response to groundwater levels. Storm events can trigger a rise in groundwater levels and increase infiltration flows. The highest infiltration flows are observed following significant storm events or following prolonged periods of precipitation. Infiltration is related to the total amount of piping and appurtenances in the ground and not to any specified water use component.

Inflow is surface water which enters the wastewater system from yard, roof and footing drains, from cross-connections with storm drains, downspouts, and through holes in manhole covers. Inflow occurs as a result of storm events such as rain and snowfall, springs or snow melt that contribute to excessive sewer flows. Peak inflow can occur during heavy storm events when storm sewer systems are surcharged, resulting in hydraulic backups and local ponding.

Previous Planning

Comprehensive planning for the sanitary sewer system has recognized that the City’s system has an I&I problem for at least the past ten years. Those plans and I&I highlights are listed below:

The constant theme of all of these past reports is that the sewer system has substantial I&I contribution to its flows. Sewage flows to the treatment plant have increased in the past ten years due to growth in the number of customers and increasing I&I has caused flows at the plant that exceed its hydraulic capacity.

State Regulations Regarding Plant Overflows

The Federal Clean Water Act prohibits anyone from discharging pollutants through a point-source into a water of the United States unless they have an NPDES Permit. The permit will contain limits on what can be discharged, monitoring and reporting requirements, and other provisions to ensure that the discharge does not hurt water quality or people’s health.

The City has a National Pollutant Discharge Elimination System Permit issued on April 29,1999, by the Washington State Department of Ecology. This permit contains discharge limitations, monitoring requirements, record keeping requirements, facility loading, operation and maintenance, and pretreatment requirements. In general, this is the operating document for the treatment plant. It also contains a description of the penalties for violating the permit.

Recent flows from the treatment plant to the river outfall have lifted lids on some of the manholes and created negative publicity for the City, even though these flows have already passed through the treatment plant. These flow conditions reflect the heavy I&I flows the plant is experiencing.

Proposed Action

It is very important to address the inflow portion by separating the storm water from the sewage lines. The costs of this work and funding for it has been planned for by the City when the last rate study was completed in 1998 and appropriate rates were adopted. This revenue has accumulated in the Utility and Cumulative Reserve Accounts. The Public Works staff and consultants are recommending that the I & I Reduction Program be undertaken in two Phases.

Phase I – Eliminate Most Obvious Sources of I & I

Phase II Second Level of I & I Removal

Table 4-6, (included below), Inflow Sources, taken from the l997 Amendment to the Wastewater Plan is an excellent place to start this process. The Six-Year CIP Improvements, also taken from the 1997 Comp Plan show preliminary budget of $240,000 for this work in 1997 dollars.

TABLE 4-6

INFLOW SOURCES(1)

 

 

 

PUBLIC ROW

LOCATION

DESCRIPTION

Manhole

4th St. and Fir Ave. (MHB8)

MH shared: Storm and S.S.

Manhole

4th St. and Bell Ave. (MH B9)

MH shared: Storm and S.S.

Manhole

First St. and Main St. (MH A1)

Storm drains to S.S.

Catch Basin

4th St. and SR2 (Post Office)

Storm drains to S.S. (roof and sidewalk)

Manhole

between Alder Ave. and Main St. and 3rd St. and 4th St. (MH B1)

Excessive seep from ground water – Storm is not connected to manhole (new in 1990)

Catch Basin

3rd St. and Main ST. (on 3rd behind Fire Station)

CB connected to S.S.

Catch Basin

5th St. and Alder Ave.

CB drains to S.S.

Catch Basin

6th St. and Alder Ave.

CB drains to S.S.

Catch Basin

Main St. and SR2 (south side of SR2)

2 CB’s drain to S.S.

PRIVATE BUSINESS

LOCATION

DESCRIPTION

Catch Basin

Cherry Hill Mobile Estates

Parking lot drains to S.S.

Catch Basin

Red Apple

Parking lot and roof drains to S.S.

(1) The eleven (11) listed sources of inflow are summarized from the 1996 Sanitary Sewer Smoke Test report, and are considered to be the most significant inflow source in the sanitary sewer system. Forty (40) additional sources were also identified in the report. The majority of these additional sources are roof drains and side sewers (Hole In The Ground Sources) located on private property.